Forewit
Shared public demo. Use fictional data. Anyone can change these projects.Join the waitlistContact

DEMO - Signal Ridge Workshop

DEMO-26005Light industrial workshop505 Signal Ridge Road, Example City - fictional siteSchematic designCommercial energy code

Fictional 12,000 sf fabrication workshop with 480 V machinery, overhead lighting and a 208/120 V support area. Demonstration data only; no real client, person or address is represented.

NEC 2020 Article 220 calculated loads for non-dwelling occupancies, from the linked feeder tree each time the page loads.

Service

Panel DP-W1

Calculated
Calculated load
138,895 VA (uses unreviewed table data)
Continuous at 125 %
142,440 VA
Maximum-load current
174.41 A
Continuous-adjusted current
179.01 A
Supply
480 V, 3-phase

Every figure here uses NEC 220 table values not yet checked against the code book.

Warning: feeder circuit load not counted. Open DP-W1 below for details.

By equipment

3 results use NEC 220 table values not yet checked against the code book. They compute; open a row to see which.

EquipmentConnected VACalculated VAMax load AContinuous AHeaviest line ASupplyState

Warning: feeder circuit load not counted.

Unreviewed data

119,323138,895 (uses unreviewed table data)174.41179.01174.41 (line A)480 V 3-phCalculated

Unreviewed data

12,66013,215 (uses unreviewed table data)20.3120.3120.31 (primary)480 V 3-phCalculated

Unreviewed data

12,66013,215 (uses unreviewed table data)46.8846.8846.88 (line A)208 V 3-phCalculated